Virtual Open House Recordings

Meeting Recording 10am-11am CT

Meeting Recording 6pm-7pm CT

Virtual Open House Presentation

Background – Project Need​

Gray map of project states highlighted in red

Southwest Power Pool (SPP)​

  • A non-for-profit, regional transmission organization (RTO) mandated by the Federal Energy Regulatory Commission (FERC) to ensure safe, reliable and cost-effective transmission infrastructure in the central region of the country​

  • In 2019, SPP identified the need for this project in its annual Integrated Transmission Plan (ITP)​

  • In 2021, through a competitive solicitation process which included 7 qualified bids, SPP selected NextEra Energy Transmission Southwest (NEET Southwest) to design, finance, build, operate and maintain this project​

For more information please visit: https://www.spp.org/​

Investing in America’s Energy Infrastructure​

NextEra Energy Inc. (NextEra) is a leading clean energy utility infrastructure company active across North America​.

Map of the United States in green showcasing multiple locations of project technology types
  • ~55,300 MW generating capacity as of year-end 2021
  • ~$119 billion in infrastructure capital deployed since 2011
  • ~81,500 miles of transmission and distribution lines
  • ~15,000 employees as of year-end 2021
  • 49 states with operations and development projects
  • 4 provinces in Canada with operations and development projects

Our Affiliates’ Existing Assets in Kansas and Missouri​

Map of the state of Kansas showcasing the many project technology locations
Map of the state of Missouri showcasing the many project technology locations
Map Key:
Green circle - NEER Wind
Blue line - NEET Transmission
 
Existing Assets:
  • Approximately $2.2 billion total capital investment
  • Approximately $10.8 milion annual payroll
  • $7.9 million annual land payments
  • $5.9 million in property taxes, 2020*
  • Approximately 260 miles of transmission lines operating in Kansas and Missouri
*Annual Property Taxes: Includes property tax and other indirect taxes. Internal data based on 2020 full year.

Wolf Creek ‒ Blackberry Project​

 

What Is The Project? ​

This project is a new 94-mile, 345 kilovolt (kV)  regulated transmission line that runs from the Wolf Creek substation (Evergy) in Kansas to the Blackberry substation (AECI) in Missouri.​

 

Why Is It Needed?​

The Wolf Creek-Blackberry Project is part of SPP’s 2019 Integrated Transmission Plan to address the needs for a more reliable and cost-effective grid. ​This project will reduce congestion and provide market efficiencies and benefits to customers.​

Where? ​

The project route traverses Coffey, Anderson, Allen, Bourbon and Crawford counties in Kansas, and Barton and Jasper counties in Missouri.​

Map of Kansas showcasing the 94-mile, 345 kilovolt (kV)  regulated transmission line that runs from the Wolf Creek substation (Evergy) in Kansas to the Blackberry substation (AECI) in Missouri.​

Project Benefits​

 

The Southwest Power Pool identified the Wolf Creek-Blackberry project as needed through its Integrated Transmission Planning Process in 2019 to provide more affordable power in the region.​

  • Expected to provide customers $23.7 million in congestion savings in its first year and an additional $377 million over the next 40 years​

  • Additional investment in the local economy during construction and the life of the project​

  • NEET Southwest is committed to using domestically-sourced materials, local vendors and workers as much as possible​

  • Estimated to provide over $28 MM in tax revenue to Kansas and $4 MM to Missouri over the next 40 years​


Routing Considerations​

 

Socioeconomic, Landowners ​Impacts​

  • Most direct route possible; lower cost for customers​

  • Reducing greenfield routing impacts for landowners by paralleling or co-locating with existing transmission lines, roads, and property lines​

  • Maximizing distances from residences and public facilities​

  • Minimizing impacts to public airports (FAA) and Military Training Zones​

 

Environmental Impacts​

  • Minimizing impacts to forested wetland and known cultural and archeological resources​
  • Minimizing/avoiding protected or sensitive species and habitat impacts​

  • Minimizing impacts to federal, state-owned, and tribal lands​

 

Infrastructure Impacts​

  • Optimize clearances to existing structures, including bridges, culverts, oil and gas wells, transmission lines,  telecom towers, and wind turbines​

     


The Electric System​

 

Transmission is a critical component of the electric system​.

Power is generated at the plant and this could be a nuclear power plant, solar site, or wind farm. It is transmitted via the transmission power lines to the substation, where high voltage power is stepped down to a lower voltage. This lower voltage power is then distributed over distribution power lines to neighborhoods, businesses, and residences and ultimately into your homes.
Power is generated at the plant and this could be a nuclear power plant, solar site, or wind farm. It is transmitted via the transmission power lines to the substation, where high voltage power is stepped down to a lower voltage. This lower voltage power is then distributed over distribution power lines to neighborhoods, businesses, and residences and ultimately into your homes.

Engineering Design​

 

The project was designed to use safe, reliable and cost-effective materials​.

Visual representation of a farm on a field near by an example drawing of a life-sized transmission line

1 Conductor

Twin-Bundled 1590 kcmil “Falcon” ACSS/TW HS conductor will be installed, exceeding SPP minimum capacity requirements to reduce loss throughout the line and offer excellent structural reliability.

 

2 Structures

Steel and spun concrete monopole structures will be installed, allowing minimal visual impact on the environment given their slim profile while exceeding structural reliability and durability requirements. The average above ground pole height will be 110 feet, the average span length will be 900 feet, and the right-of-way width will be 150’, which is typical for 345-kV transmission lines.

 

3 Insulators

Braced post insulator assemblies will be installed in a delta configuration on the pole to support the conductor wires.

 

4 OPGW

Optical Ground Wire (OPGW) will provide the best possible protection for optical fibers, reliable lightning shielding, excellent corrosion performance, and will exceed the required fault current carrying capacity.

 

5 Foundation

Typical foundations installed will include direct embedded poles with crushed rock or unreinforced concrete backfill with an average pole diameter of 4.5 feet at the groundline.  Angle structures will also be direct embedded poles supported by guy wires.  Self-supporting structures placed on drilled shaft foundations will be installed at select locations to support line crossings and other constraints.


Construction Activities​

 

With Safety at the Forefront ​of Everything We Do, ​NEET Southwest Will:

  • Construct the line with qualified, insured, experienced contractors with proven safety records and that use protocols to help prevent the spread of COVID-19​

  • Require its contractors to minimize disturbances, protect landowners and their property​

 

Activities That Will Happen Along the Project’s ​Right-of-Way (ROW):​

  • Meet with landowners to address issues and questions​
  • Clear ROW for construction access​

  • Install new foundations, poles and wires​

  • Clean up and restore the ROW as close to original condition as possible


Right-of-Way Easements​

 

Working with Landowners​

NEET Southwest is securing options for easements from landowners whose land will be crossed by the transmission line. Following regulatory approvals of the project, NEET Southwest will finalize the purchase of the easements.​

Crews and contractors may access the rights of way to conduct the following activities while the project approval process is underway:​

  • Surveying​

  • Cultural and natural resources assessments​

  • Wetlands delineations​

  • Soils testing​

NEET Southwest will work with landowners on an ongoing basis throughout the construction, clean up phase of the project, and beyond.​


Project Timeline​

Regulatory Approvals are planned to happen in the year 2022 from quarter one through quarter four. ROW Acquisition is planned to happen in the year 2022 from quarter one through the year 2023 quarter two. Design and Engineering is planned to happen from year 2022 from quarter one through quarter three. Environmental Permitting is planned to happen from year 2022 quarter two through year 2023 quarter two. Procurement is planned to happen in year 2022 quarter four through year 2023 quarter three. Construction is planned to happen in year 2023 quarter three through year 2024 quarter four. Commissioning is planned to happen in year 2024 quarter three through year 2024 quarter four. Project In-Service is planned to happen in year 2025 during quarter one.

 

Regulatory Approvals: 2022 Q1-Q4
ROW Acquisition: 2022 Q1-2023 Q2
Design and Engineering: 2022 Q1-2023 Q3
Environmental Permitting: 2022 Q2-2023 Q2
Procurement: 2022 Q4-2023 Q3
Construction: 2023 Q3-2024 Q4
Commissioning: 2024 Q3-2024 Q4
Project In-Service: 2025 Q1
 
Note: Subject to Regulatory approvals.

Operations and Maintenance​

 

NEET Southwest focuses on reliability and safety  standards for operating transmission assets​.

 

To do this, NEET Southwest:​

  • Monitors system on a 24-hour basis from its state-of-the-art operations control center​

  • Performs regular, preventative, time-based inspections​

  • Makes timely repairs when needed​

  • Monitors and removes vegetation in ROW to help ensure the safe and reliable operation of the transmission line​

  • Supports by 70 technical staff in locations near the Project and one location within 30-minute drive from the Project mid-point ​

NEET Southwest provides landowners notice before accessing the ROW to perform scheduled maintenance. In the unlikely event of an emergency, NEET Southwest will immediately deploy local crews to ensure safety and resolve any issues.​