A map of the Wolf Creek-Blackberry transmission line route reaching from Kansas to Missouri.

Project Overview


NEET Southwest energized the Wolf Creek-Blackberry transmission line ahead of schedule and on budget, strengthening the electric grid for customers in Kansas and Missouri. This new approximately 92-mile 345 kV transmission line connects the Wolf Creek substation in Coffey County, Kansas to the Blackberry substation in Jasper County, Missouri. NEET Southwest was awarded the project in 2021 and it was energized in May 2025. 

The project is part of the 2019 Integrated Transmission Plan approved by SPP in October 2019 to address the need for a more reliable and cost-effective grid. This project will reduce congestion and provide market efficiencies and benefits to ratepayers.


Regulatory Filing

Project Benefits

  • Leads to lower electricity costs for customers
  • Enhances the reliability and resiliency of the electric grid

  • Creates job opportunities in the short and long term

  • Spurs investment in the local economy during construction

  • Supports public health and safety through access to reliable electricity


Environmental & Visual Considerations

  • Conducted rigorous environmental analyses to limit impacts on wildlife, sensitive habitats and natural resources

  • Coordinated with federal and states agencies to identify protected species found along the route

  • Selected monopole structures to minimize tree clearing and agricultural impacts

  • Incorporated considerations for visual impacts into routing study
     

 

Project Timeline


Below is a timeline of the Wolf Creek-Blackberry project.

  • Q4 2022: Regulatory approvals.
  • Q2/Q3 2023: Right-of-way acquisition completed.
  • Q3 2023: Environmental completed.
  • Q3 2025: Construction and commissioning completed.
  • January 1, 2026: SPP Required ISD.

Project Design

NEET Southwest’s design provides the most value to customers with safe, reliable and cost-effective components and materials.